The project includes the expansion of the Lot 2A passenger terminal on the north side through the creation of new additional volumes and the redevelopment of the existing spaces of the...
The overall project, which will be completed by 2022, involves the design and build of civil works for about 13.6 km of new double-track railway line, including 2 bridges, three tunnel...
Il passante della nuova linea Alta Velocità/Alta Capacità si sviluppa per circa 7 chilometri in sotterranea con due gallerie parallele mediamente a circa 20 metri di profondità,...
The section from Treviglio to Brescia is 39 km long; the project approved by the CIPE (Interministerial Committee for Economic Planning) involves the construction of a new section...
The general objective of the project is the promotion of mobility on railways along Pan-European Corridor IV, through the restoration and upgrading of the existing Brasov to Simeria...
Modernization and development affecting the CIRCUMVESUVIANA RAILWAY, particularly the TORRE ANNUNZIATA – POMPEI Stretch: the works consist of the burying of the Station of Pompei, the...
Construction of the multi-motorway link on the Tirreno-Brennero Motorway, junction with the Autostrada della Cisa A15 motorway-Autostrada del Brennero A22 Fontevivo (Parma) – Nogarole...
Il Lotto 1 rappresenta il primo tratto della nuova autostrada Sebes-Turda. L’ autostrada, avente un’estensione complessiva di 70 km, è collocata nella Romania occidentale e collegherà...
Il progetto consiste nello scavo con TBM doppio scudata di due gallerie idrauliche aventi diametro pari a 3,70 m e lunghezza complessiva pari a circa 12 Km. Le due gallerie localizzate...
In the wider redevelopment of the Polish road network, funded by European Community Union, the works include the Design Build of three road sections of the Expressway S5 which will...
The project represent an important link road corridor that crosses the northwest of Moldavia between the cities of Balti and Sculeni and is part of the international connection between...
The 3 projects are part of the extension of the existing lines of the Paris Metro, “Grand Paris Express” which is set to double, over the next ten years, the current underground...
The project consists of the construction of the lot of the new Line 15 South Paris metro stations within Noisy Champ (not included) and Bry Villiers Champigny (not included).
Extension of Line 11 of the Metro Paris from terminal of Mairie des Lilas station.
The project, located in the northeast of Poland near the border with Lithuania, consists of the construction of 24 km of a new motorway from the city of Suwalki to the border, and...
Impresa Pizzarotti, in joint venture with another company and with a 50% share, will realize the third lane of the A4 motorway in the stretch from Alvisopoli (VE) to Gonars (UD). It...
The project represents the first Pizzarotti infrastructural work in Peru. It completes the motorway between the cities of Arequipa and La Joya. The main structure of the bridge, with a...
Construction of civil works and related works of Lotto Castagnola, with reference to the construction of the AV/AC “Terzo Valico dei Giovi”.
The project consists in the upgrading of various artifacts of the railway line Bellinzona / Luino, track Ranzo - Cadenazzo developing on about 16km in a highly urbanized area. The...
The construction of the new subway line includes a tunnel of about 6 km, two new underground stations (Le Bourget Airport and Triangle de Gonesse), six auxiliary works (mainly...
The intervention includes the executive design and construction of the Naples-Bari railway line, Frasso Telesino-Telese line between the pk 16 + 500 of the future Cancello-Benevento...
Design and execution of the works to double the line and increase speed on the Cancello-Frasso Telesino line, an important part of the new High Speed/High Capacity Naples - Bari line...
The project consists in the construction of the finalstretch of the Naples - Bari route and is strategic in the overall reorganization of the metropolitan, regional and long-distance...
The award, which took place following a tender at European level, represents a new important order within the strategic plan of Impresa Pizzarotti. The project is part of the...
The contract, awarded by Pizzarotti SA,concerns the upgrading of the Melide-Grancia Tunnel on the Lugano Sud - Mendrisio motorway, with an extraordinary maintenance of the supporting...
Chuquicamata, detta anche Chuqui, è la miniera di rame a cielo aperto più grande del mondo. Sita in Cile nella Regione di Antofagasta, a 15 km a nord di Calama e a 245 km a nord-est...
Construction of the Faido shaft for the access to the Gotthard base tunnel. Excavation of a 2760m long passage with an average section of 60m² and an average gradient of 12.7%....
Construction of the station interconnection between networks of intercity TGV - RER Roissy airport. The exchange module between high speed train stationand the metro regional airport...
Construction of the Viaduct of AIN TURK BOUIRA – East-West Motorway Section Lakhdaria - RN5, in the Municipalities of Djebahia and Ain Turk (Wilaya di Bouira), approx. 100 km from...
Erection of a reservoir for collecting the overflow of the Parma Torrent, with the consequent securing of the entire Parma province in addition to the elimination of any...
The work consists of the construction of the twin tunnels of Oudayas, in an urban setting, consisting of two entry ramps of 518 m, two artificial tunnels totalling 125 m, a natural...
The Milan-Bologna section of High Speed Railway – carrying out of civil works to reposition the old Modena railway line from PK 37.903 to PK 48.155.
Construction of the Brenner base tunnel: Aica-Mules exploratory tunnel with a length of 10,477m, with a cross section of 31.15 m2 and a diameter of 6.3m. - The excavation was carried...
1st and 2nd sections of the Cluj bypass, for a distance of 18.7 km – The work consists of a 1st section with 4 viaducts totalling 1671m in length and an average height of 30m, with a...
Construction of a 60m long approach cutting and a tunnel and passage with a length of 210m in loose material composed mainly of gravel and silt. Retention of the cutting by secant...
The works consist of two adjoining bridges with an approximate length of 155m, one carrying four lanes of traffic and other being a covered footbridge with three floors. The bridges...
The Pedemontana Lombarda is made up of three lots: Section A of the Pedemontana Lombarda Motorway runs from the intersection with the A8 Milan-Varese motorway, in the municipality of...
Construction of the new railway site in the urban stretch through Rome of the Rome–Naples section of the Italian High Speed Railway Network, between progressive km. 2+273 and km. 4+420...
Lot 854 “Underground works and cut and cover tunnel at Vezia” is for the construction of the entrance in Vezia to the Ceneri Base Tunnel including approximately the first 550m of the...
Realizzazione della Stazione Garibaldi della linea 1 e della Stazione Arco Mirelli della linea 6 della Metropolitana di Napoli. La Stazione Garibaldi consiste in un pozzo di Stazione...
Construction of the tramway system of the city of Constantine – stretching for 9 km from the terminal of Zouaghi to the station of Ben Abdelmalek – The line runs from the city’s...
The link between Bucharest, the north area and the city of Brasov is part of a Main Program of rehabilitation of the road network of the whole country. It includes 7 viaducts and 5...
Lot 853 “Interventions on the North Portal Vigana area” consists of a twin-tube tunnel and two caverns, one of which is partially under the surface of the motorway. The external works...
Concession for Design, Build and Management of the new Highway which connects the cities of Brescia, Bergamo and Milan. It represents the first project in Italy completely financed...
Modernization and adjustment works for the construction of the hard shoulder of the Salerno - Reggio Calabria A3 Motorway – Section 2 stretch 6 single lot - from km. 286+000 (Altilia...
A3 Motorway Salerno-Reggio Calabria: works for modernizing and upgrading to CNR standards solution 3+3 lanes plus respective hard shoulders, Section 1, Stretch 5 Lot 4 between the...
Building of two tunnels each approx. 6.3 km and of the caverns of the multifunctional area of the Gotthard base tunnel. Access to the underground sites only through two vertical wells...
Construction of the Catania-Siracusa expressway, between the town of Passo Martino, along Catania Service Axis and km 130+400 of highway SS114. For nearly 25 km, of which 6 km are...
The terminated project features: two concrete gravity dams, 55m high each with ancillary works, a connection tunnel between the two reservoirs, a pressure-system transfer tunnel, a...
The stretch of the new Milan East External Bypass (TEEM) extends for a distance of about 40 km from Melegnano (intersection with the A1 Milan-Bologna motorway) and Agrate (intersection...
The Lugano – Bellinzona Viaduct (Lot 781) has an overall length of 1000m and involves the construction of special foundations (bored piles and jet-grouting consolidation), substructure...
The project implies the doubling of the existing hydroelectric plant of Kalayaan with the execution of a new plant with two turbines of 175 MW each, positionned at - 40.5 metters below...
Realization of engineering works of the Methane-producing Terminal of Fos Cavaou (France, Marseille)
Construction of Naturno-Stava ring-road and link with Val Senales Highway n 3 between km 180,600 and km 188,930 of Stelvio Highway n 38.
The most significant construction Lot 2.2. is the 1.632 m long Fontanellato Artificial Tunnel, to be built in reinforced artificial concrete, partly below ground. The path is over...
Construction of the Structural Works for the East - West Zennouna - Bordj Bou Arreridj motorway section, stretching for an overall length of 18 km, in the Municipalities of El Achir...
Infrastructural development of the Pontremoli route, laying of second track on the S. Stefano Magra - Aulla Chiesaccia stretch. Implementation of civil engineering works for the...
Works relative to the utilization of the waters flowing into the artificial lake of Santa Rosalia on the river Irminio – Feeder channel in the Municipalities of Ragusa, Modica and...
Building of Busto Arsizio/Malpensa railway link. Installation of a twin-railway track between the station of Busto Arsizio F.N.M.E. (excluded) and the perimeter of Malpensa Airport...
The project consists of two double-barrel tunnels at "Uriol" and "Petit Brion". Uriol has a Jurassic-era lime-scale massif, while the Petit Brion crosses a lime scale quartz-clay...
Trench Quadrupling and artificial railway tunnel between CADORNA and BOVISA on the MILANO - SARONNO line. The tender consists of special foundation works, civil works, civil and...
Construction of new passenger terminal and civil works at the International Airport.
Integrated design and construction relating to Milan-Bologna railway line quadrupling, under Cepav Uno Consortium where Impresa Pizzarotti C. S.p.A. holds a stake of 14,15%. Within...
Excavation in loose material for 820m of double tube tunnel in the Bodio section of the Gotthard Base Tunnel. The two tunnels pass through a cone of detritus formed by loose material...
Construction of penstock for the east canal and water distribution network in the coastal area up to Imera Varzo II VB.
The barraging works of "Medau Zirimilis Carru Segau" together with the related works (evacuators, derivation tunnels etc.) represents the reservoir on "Rio Casteddu" situated in...
La realizzazione del tunnel è parte integrante del progetto per la deviazione della cittadina di Saint Béat (Haute Garonne – Francia). In particolare, il progetto consiste nel...
I lavori di realizzazione del nuovo tunnel di Viggianello sono parte integrante di un progetto che riguarda la deviazione della città di Propriano (Corsica – Francia). La deviazione...
Completion of the connection track along A35 motorway (conversion of the existing category C road to the A-motorway) for about 5,6 km and the direct interconnection between the A35...