The start-up work of the project “Bucharest Highway A0 North Lot 1” continues
The start-up work of the project “Highway Bucharest A0 North Lot 1” continues with the advancement of archaeological research activities on the field for which 10 machines (excavators, dozers and trucks) and 60 workers were used. Eleven sites were completed last month, with activities currently taking place exclusively at site no. 2, the largest and most complex.
The work of organizing the construction site, including the supply of earth excavated for deposits along the route, intended to be used as filling material in the body of the highway. In parallel, the land is being cleared with dozers and the motorway strip is being cleared in the two forest areas of Raioasa and Buciumeni.