Progress of works in Saint-Laurent-du-Maroni

Work continues on the Saint-Laurent-du-Maroni Penitentiary Citadel in French Guiana, a major, complex project requiring coordination, specialist skills and solid organisation. On the foundations front, two teams are working in parallel to construct the piles.

The aim is to free up the first buildings for the heavy carpentry teams to move in and start assembling the first two cranes. Excavation work has also been ongoing for several months, a key step in enabling the filling work and start-up of nearby buildings.

Prosegue inoltre da diversi mesi la realizzazione degli scavi, passaggio chiave per consentire i lavori di riempimento e l’avviamento degli edifici nelle vicinanze.

At the same time, the logistics teams are working to secure the various bases and ensure the transfer of our equipment from Guadeloupe, thus enabling operational continuity in a complex environment.

This progress demonstrates Impresa Pizzarotti’s ability to operate effectively even in challenging international scenarios.