Port of Genoa: Final launch of the MSC Viaduct deck successfully completed
The final launch of the MSC Viaduct deck between piers P3 and P4 has been successfully completed as part of the Road Infrastructure Works Contract at the Port of Genoa, entrusted to Impresa Pizzarotti & amp; C. Spa in ATI with CMM Rizzi Spa.
As with the previous launch, the deck was moved along the port roads using a pair of self-propelled trolleys and subsequently taken over by a crane that kept it under fire until the welding and safety operations were completed.
With the metalwork completed, at the beginning of the new year the running boards with reinforced concrete slabs above them will be laid, the access ramps to the new deck will be completed, the asphalt paving will be installed, and the road barriers will be installed. Another important project that will revolutionize the internal traffic flow of the Port of Genoa will be completed.