14 April 2026

A0 Bucharest North Highway – Lot 1: progress report

After nearly three months of downtime due to particularly adverse weather conditions, construction activities have resumed and are now proceeding at a steady pace across all operational fronts.

Work is currently underway on the embankments and major engineering structures, along with essential tasks such as the installation of manholes, the relocation of utility networks, and environmental remediation—all key elements for the overall development of the infrastructure.

To date, 45.22% of the project has been completed, thanks to the efforts of over 800 people and the use of hundreds of construction vehicles, confirming the strong commitment to the project.

Lot 1 of the A0 North Motorway represents a strategic infrastructure for mobility in the Bucharest area, helping to improve connections between major thoroughfares and make traffic flow more smoothly throughout the entire metropolitan area. ()

The entire Pizzarotti–Retter JV team is fully motivated and focused on achieving the goal: opening the road to traffic by 2026, thereby making a concrete contribution to the development of mobility in Romania.